Applied Digital's $36 Billion Backlog Comes With a Debt Test

Applied Digital has 1.41 gigawatts under lease and $36 billion of base-term contracted revenue, but construction requires heavy borrowing. A bond downgrade shifts attention from demand to the price of financing the next campuses.
Applied Digital's operating story has rarely looked stronger, yet its financing risk is becoming harder to ignore. The company reported 1.41 gigawatts of leased critical IT load and $36 billion of contracted revenue over initial lease terms. Including renewal options, management puts the figure at $86 billion.
Those contracts explain the bull case. Long-term, take-or-pay leases with hyperscale customers can support predictable revenue once facilities are operating. Applied Digital's first-quarter revenue reached $341.9 million, up 432.4% from a year earlier, and adjusted EBITDA rose to $64.4 million from $0.5 million. The high-performance-computing hosting segment produced $262.6 million of revenue.
The construction bill arrives before much of the rent. The company reported $5.0 billion of debt and $4.2 billion of cash and restricted cash at May 31, then issued $1.59 billion of 7% senior secured notes for another building at Polaris Forge 1. It plans additional financing for Polaris Forge 3, Delta Forge 1 and Delta Forge 2.
JPMorgan analysts downgraded Applied Digital's project-finance bonds to Neutral from Overweight, citing potential supply from the coming debt raises. The stock fell 4% in the session described by the source, while other leveraged AI infrastructure names also declined.
The tension is not whether AI demand exists. It is whether the company can fund construction at rates that leave enough value for shareholders after interest, depreciation and stock compensation. Applied Digital reported a $184 million GAAP net loss in the quarter, partly reflecting non-cash fair-value charges but also showing the distance between rapid revenue growth and bottom-line profitability.
The next financing terms are therefore more important than another capacity announcement. A well-priced deal could validate the contracted-backlog model. Higher coupons or stronger collateral demands would transfer more of the project's economics to creditors. Investors should track funded capacity, tenant concentration and cash required before each lease begins.
Continue your WULF research
Related News
Cipher’s Zero-Coupon Notes Show the Hidden Cost of AI Data Centers
Cipher Digital’s $850 million zero-coupon convertible offers cheap stated interest, but conversion dilution, repayment obligations and project execution reveal the real financing cost behind data-center expansion.
AI Infrastructure Stocks Rebound, but Contracted Power Is the Real Test
Applied Digital, TeraWulf and IREN rebounded after a selloff, yet investors still need to clearly distinguish contracted capacity from powered, funded and revenue-producing data centers.
Bank OZK's Rising Dividend Is Well Covered, but Credit Still Sets the Limit
Bank OZK raised its quarterly dividend for a 65th straight quarter. A payout near one-third of earnings provides room, while construction-loan credit remains the main constraint.
Moderna's Melanoma Data Must Justify a Rally Analysts Do Not
Moderna rallied ahead of full Phase 3 melanoma data due Oct. 24, even as Goldman Sachs kept a Neutral rating and set a target well below the share price.
Novavax's Selloff Puts the Sanofi Partnership Under the Microscope
Novavax fell harder than the broader biotech market as investors reconsidered a partner-led business. Sanofi gives the company reach, but royalty and milestone timing remain outside Novavax's control.
Parabilis Heads Into ESMO With Strong Early Data and a High Bar
Parabilis will present updated zolucatetide data in desmoid tumors on Oct. 24. Early responses were strong, but investors still need durability, safety and a credible Phase 3 dose.















Latest comments